Gartech Elec. Contr. Corp. v Coastal Elec. Constr. Corp.
2009 NY Slip Op 07306 [66 AD3d 463]
October 13, 2009
Appellate Division, First Department
As corrected through Wednesday, December 9, 2009


Gartech Electrical Contracting Corp.,Respondent,
v
Coastal Electric Construction Corp.,Appellant.

[*1]Tunstead & Schechter, Jericho (Jeremy Kalina of counsel), for appellant.

McMahon, Martine & Gallagher, LLP, Brooklyn (Patrick W. Brophy of counsel), forrespondent.

Judgment, Supreme Court, Bronx County (Yvonne Gonzalez, J.), entered August 28, 2007,after a jury trial, awarding plaintiff $244,441.99, inclusive of interest and costs, affirmed, withcosts.

"[T]he question of whether a verdict is against the weight of the evidence involves what is inlarge part a discretionary balancing of many factors (see Mann v Hunt, 283 App Div140). For a court to conclude as a matter of law that a jury verdict is not supported by sufficientevidence, however, requires a harsher and more basic assessment of the jury verdict. It isnecessary to first conclude that there is simply no valid line of reasoning and permissibleinferences which could possibly lead rational [persons] to the conclusion reached by the jury onthe basis of the evidence presented at trial" (Cohen v Hallmark Cards, 45 NY2d 493, 499[1978]). The party seeking this finding faces a "lofty hurdle" (Adamy v Ziriakus, 92NY2d 396, 400 [1998]). As a result, "in any case in which it can be said that the evidence is suchthat it would not be utterly irrational for a jury to reach the result it has determined upon, andthus a valid question of fact does exist, the court may not conclude that the verdict is as a matterof law not supported by the evidence" (Cohen, 45 NY2d at 499).

A fair interpretation of the evidence (see McDermott v Coffee Beanery, Ltd., 9 AD3d 195, 205-206[2004]) supports the jury's findings that defendant breached the parties' contract, that the partialwaivers signed by plaintiff were coerced by economic duress, and that plaintiff sustained thedamages it claimed.

The dissent disagrees with the jury's verdict, characterizing the testimony of plaintiff'spresident as incredible and contending that the judgment should be vacated and the matterremanded for a new trial. However, "[d]isputes as to proof are for the jury to resolve in assessing. . . the credibility of the witnesses" (Manne v Museum of Modern Art, 39 AD3d 368 [2007] [internalquotation marks omitted]), and the jury's "resolution of any conflicting evidence is entitled todeference" (id.).

The facts are set forth in the dissent. In the interest of brevity, we will not provide a separatestatement of the facts, although we do not agree with all of our colleague's characterizations ofthe testimony presented at trial.

Plaintiff's president testified that he believed the installments listed in the purchase order[*2]in question would be paid in full on the date listed regardlessof the amount of work completed as of those dates. He further testified that, at least in the earlypart of its performance of the purchase order, its electricians had to wait until certain other workwas done, such as the installation of the sprinkler system by plumbers, before they could fullystaff the project. As a result, according to plaintiff's president, it made sense to have fewerelectricians working at the beginning of the project and more as the project neared completion.Although there was some equivocation as to the number of electricians plaintiff committed tohave on the job at the beginning of the project, this was an issue for the jury to take intoconsideration during its deliberations. The jury could easily have credited this testimony insteadof defendant's vice-president's testimony that plaintiff was not providing enough workers in theearly stages of the job, requiring defendant to employ its own electricians and deduct that costfrom plaintiff's invoices. Although the purchase order provided that "[f]ailure to deliver materialsor services in a timely fashion will release contractor from any obligation to purchase implied bythis order," nowhere in the purchase order is there any indication that plaintiff was to havecompleted a certain amount of work on the specified payment dates in order for a particularinstallment to be paid in full. Nor can it be said that plaintiff is claiming that it needed to donothing to get paid, as the dissent seems to characterize plaintiff's position, as plaintiff'spresident clearly testified that his concept of the project was to provide the bulk of hiselectricians toward the end of the project, when the other trade craftsmen had completed theirwork and were out of the way. As plaintiff's president testified on cross-examination: "Most ofthe work is going to be done closer to the end of the job. So the last two weeks or the last monthwe could be using, you know, it could be any amount of electricians there. We could be using upto forty electricians at the end of the job in the last two weeks to do different things. . . So all the equipment that the other trades working needs to be out of thebuilding, and the electricians was doing the testing for—need to have clear reign to pullstations and go back and forth to the main board . . . [W]e could need forty guys atthe end. There was never a discussion about exactly how many electricians we were going to useat any one time."

A fair interpretation of this testimony supports the jury's implicit conclusion that plaintiff didnot fail to deliver services in a timely fashion.

Moreover, the jury was free to reject defendant's testimony and documentary evidenceregarding its claim that plaintiff did not have a sufficient number of electricians on the job site totimely complete the work. The dissent argues that defendant submitted documents (consistingmostly of its own letters to plaintiff) to support its claim that plaintiff failed to provide adequatepersonnel to complete the job, and that there was no written evidence from plaintiff thatprotested or contradicted defendant's letters. However, it is undisputed that one of the reasonswhy plaintiff was hired by defendant as its subcontractor was the fact that Ray Evans, anemployee of defendant, had previously worked with plaintiff's president and knew his work.Plaintiff's president testified that he normally would have responded to defendant's letters inwriting but, because of his relationship with Evans, he instead had oral discussions with Evansand defendant's vice-president. In fact, when asked about any writings sent by defendant toplaintiff, plaintiff's president testified on cross-examination that, while he did not respond toeach of defendant's letters in writing, "I was in contact with, I was in contact with Ray, and um,and we [*3]were discussing constantly and he was the one thatwas actually writing, doing the paperwork." Defendant did not call Evans as a witness to rebutthis testimony. Moreover, plaintiff's president also testified that with respect to plaintiff's invoicefor the second installment payment, he deducted defendant's labor costs under duress. Hetestified, again on cross-examination:

"Q. Then he does a calculation of, um, Costal's cost, that they will need to deduct in order tomake up the—for the people that they have provided to the job site; do you see that?

"A. Yes. I see that yes, and I never agreed to this.

"Q. Then they send you this letter and then before you can get payment, you have to sign apartial waiver and release of lien, correct?

"A. Yes.

"Q. So is this why you testified earlier that you were forced to sign this?

"A. I need to get my money and I signed it, yes, to get the money."

The jury obviously credited this testimony and, on this record, it cannot be said that it wasunfair to do so.

Nor do plaintiff's invoices provide support for defendant's position that plaintiff failed toprovide adequate workers to perform the necessary work in a timely manner. While the dissentcorrectly points out that "plaintiff provided its certified payroll records to defendant as it wasprocessing the installment payments," the actual invoices/payment requisitions that plaintiffsubmitted to defendant neither included nor referenced payroll records.[FN*] Defendant's letters to plaintiff do not suggest that plaintiff had to submit payroll records in orderto be paid, and such are not required pursuant to the terms of the purchase order. As noted, thepurchase order itself, which was drafted by defendant, does not provide for completion byplaintiff of a certain percentage of the work to receive the first payment, an additional percentageof the work to receive the second payment, and so on. In fact, plaintiff's president testified oncross-examination that defendant did not pay the full amount of the first installment because it"didn't have the money to pay me." The following colloquy took place:

"Q. They told you that they did not have the money to pay you?

"A. Yeah. They were—um, you know, they were like let's work, let's work it out nextmonth and partial payment and we'll work it out next month."

This presented a clear conflict in the testimony that was for the jury to resolve. The jurycould fairly conclude that plaintiff was paid less than the full amount of the first installment notbecause it failed to deliver services in a timely fashion, but because defendant did not have the[*4]money. The jury could also fairly find that plaintiff's requestfor $250,000 instead of $237,500 (the amount set forth in the purchase order) in its secondrequisition resulted from, as plaintiff's president testified, defendant's failure to pay the fullcontract amount requested in the first invoice ($80,000 instead of $107,350), and not because itclaimed it did additional work on the project. This too is an issue of credibility that the juryresolved in plaintiff's favor.

Plaintiff's claim that defendant guaranteed that it would make a profit, when viewed in thecontext of the entirety of the negotiations leading up to the contract, does not strain credulity assuggested by the dissent. Plaintiff's original proposal to install the fire alarm system was in theamount of $1,375,667. Defendant found this price to be too high, and the parties entered intonegotiations, eventually agreeing on a price of $1,130,000. According to plaintiff's president'stestimony, defendant said that plaintiff's original proposal was "overkill on the profit" and that"we [defendant] are sure you [plaintiff will] make money if you give us the better price, and willstill make . . . a lot of profit." The jury could fairly have credited plaintiff'stestimony in this regard in arriving at its verdict.

Finally, plaintiff is not impermissibly seeking to recover on a theory of quantum meruit. Thetrial court instructed the jury, without objection, "The non-breaching party is allowed to rescindthe contract . . . It may . . . sue in quantum meruit for the reasonablevalue of the services that it provided to the breaching party, less any payments already received"(see Whitmyer Bros. v State of New York, 47 NY2d 960, 962 [1979]).

In brief, the credibility and weight of plaintiff's president's explanations as to why hecomplied with certain demands from defendant, such as the production of payroll records, anddid not respond in writing to defendant's letters raised issues that were appropriately left to thejury, and it cannot be said that the jury's conclusions are against the weight of the evidence.

A court may not interfere with the fact-finding function of a jury because it would haveevaluated credibility in a different manner (McDermott v Coffee Beanery, Ltd., 9 AD3dat 206; Rivera v 4064 Realty Co.,17 AD3d 201, 203 [2005], lv denied 5 NY3d 713 [2005]).

Since we find the jury's verdict is based upon a valid line of reasoning supported bysufficient evidence, we affirm the judgment entered in this case.

While defendant's challenge to plaintiff's summation is not preserved, we nevertheless findthat the challenged remarks generally constituted fair comment on the evidence and did notdeprive defendant of a fair trial (see Hancock v 330 Hull Realty Corp., 225 AD2d 365,365 [1996]). Concur—Sweeny, Renwick and Freedman, JJ.

Friedman, J.P., and McGuire, J., dissent in a memorandum by McGuire, J., as follows:Defendant was hired by an electrical subcontractor on a project to build a two-storyadministrative facility for the Metropolitan Transportation Authority (MTA). Defendant, in turn,retained plaintiff to install the facility's fire alarm system, a job that entailed installing conduit,pulling wire, installing fire alarm devices and testing the system. The entire project, includingplaintiff's work, was a "fast-track" job.

The parties signed a purchase order agreement, dated March 1, 2004. The agreementprovided, among other things, that the "[p]roject is as per plans and specifications," that plaintiffwould supply the "[l]abor to install [the] complete fire alarm system" and that the work was to be[*5]completed by June 7, 2004. Plaintiff was to be paid a total of$1,130,000 under the agreement, pursuant to the following schedule:

º Payment no. 1—March 29, 2004—$107,350

º Payment no. 2—April 26, 2004—$237,500

º Payment no. 3—June 07, 2004—$237,500

º Payment no. 4—June 28, 2004—$276,450

º Final payment—July 26, 2004—$271,200.

However, the payment schedule was "subject to change." The "Terms" portion of thepurchase order stated, in relevant part, that the "[f]ailure to deliver materials or services in atimely fashion will release contractor [i.e., defendant] from any obligation to purchase impliedby this order."

Plaintiff began working at the job site on or about March 1 when the purchase orderagreement was signed. Plaintiff did not complete the work required by the purchase order andwalked off the job site on June 9. The parties offer competing versions of what occurred betweenthe date plaintiff began work and the date it abandoned the job site. The parties' accounts of thefacts are discussed below.

In its complaint, plaintiff alleged that defendant breached the purchase order agreement andseeks to recover $243,341.99, the difference between the amount of money it spent on theproject ($375,600.65) and the amount it was paid by defendant ($174,491.57) plus its "allowancefor overhead and profit" ($42,232.91). Defendant asserted a counterclaim for breach of thepurchase order agreement, seeking damages for the costs it incurred to complete the installationof the fire alarm system ($472,080).

Plaintiff's theory of its case was that defendant was required to make the installmentpayments on the dates specified in the purchase order regardless of the extent to which plaintiffhad completed its work; defendant failed to make the payments, forcing plaintiff to incur debt toperform its work; and defendant, without plaintiff's consent, used its own workers to perform thework and charged plaintiff for the costs it incurred to complete the work.

Defendant's theory of its case was that the purchase order was a "lump-sum" contractpursuant to which plaintiff would submit requisitions reflecting the amount of work plaintiff hadperformed and defendant would issue installment payments based on the amount of workcompleted. According to defendant, plaintiff failed to advance the work as anticipated under thepurchase order and failed to assign sufficient numbers of electricians to the job. Consequently,defendant was required to assign its own workers to augment plaintiff's work force. Defendantclaimed that pursuant to an oral agreement the parties made after executing the purchase order, itwas entitled to charge plaintiff for the costs of augmenting the work force and to deduct thosecosts from plaintiff's installment payments.

On its case, plaintiff presented only one witness, its president, who testified that he believedplaintiff would be paid the installment payments in full on the dates listed in the purchase orderregardless of the amount of work plaintiff had completed. This was so, according to plaintiff'spresident, because defendant did not provide plaintiff with "mobilization" money before thework commenced. Plaintiff's president testified that defendant guaranteed him that plaintiffwould make a profit on the project.

On cross-examination, plaintiff's president was equivocal in his testimony regarding whetherhe promised defendant prior to the execution of the purchase order that plaintiff would employ atleast 15 electricians on the project. Thus, when asked if "[d]uring your preliminary meetingswith [defendant], didn't you promise [defendant] that you would employ between [*6]fifteen and eighteen electricians on the project," plaintiff's presidentresponded: "I don't, I don't remember a number like that because my, my understanding of thejob is that as soon as we are able to use more electricians we would use as, as much [sic]electricians as we need, and, therefore, we would end up with thirty at the end of the job, or wecould end up with twenty at the end of the job, depending how the job—because most ofthe equipment is going to be done at the end of the job anyway. Most of the work is going to bedone close to the end of the job. So the last two weeks or the last month we could be using, youknow, it could be any amount of electricians there . . . There was never adiscussion[ ] about exactly how many electricians we are going to use at any one time. . . I could not have told them exactly how much [sic] electricians."

By a requisition dated March 24, 2004, plaintiff requested from defendant the firstinstallment payment of $107,350. The requisition did not delineate the work plaintiff hadperformed on the job site and merely demanded the payment specified in the purchase order.Defendant's vice-president responded to the requisition in a letter dated March 31 stating:

"As per our discussion this morning, we will be supplying approximately 10 men with aForeman to perform work associated with your contract for the Fire Alarm system at the abovereferenced project. The work performed by our work force will need to be deducted from yourcontract accordingly. Please be aware that this will affect the payment schedule that was put inplace at the beginning of the project. In order to see how it will affect future payments, we reallyneed to see how the job progresses a little bit before assessing the costs associated.

"In terms of payment #1, we will need to reduce the payment slightly based on the fact thatwe will be adding significant manpower with large cash flow needs to perform your contractwork. I have received your certified payrolls for the weeks ending February 25, 2004 and March3, 2004. They show for the month of February 2004 a total of 259 Regular Hours were workedby [plaintiff] personnel (42 Foreman, 140 Journeyman, 77 Apprentice). Your total certifiedpayrolls for those two weeks show 462 Regular Hours (63 Foreman, 224 Journeyman, 175Apprentice). Your approximate total cost for these weeks is $31,000. We know that you havebeen working onsite since this and have worked an additional 1,200+ hours through 3/24/04.Therefore, for payment #1, we are offering to release $80,000 immediately to [plaintiff]. A newpartial waiver of lien is enclosed for your review and signature. As soon as the waiver isreceived, your check will be available . . . . Please understand we are doingeverything we can to work with you on this project and make sure both of our companies areprotected. Our goal is to build a successful project for our client, and in doing so, we need toensure that the specific demands in terms of performance and scheduling of this contract are met,which is why it is essential that we step in and make some adjustments to your current contract."

Plaintiff's president acknowledged that he received and read the letter but denied agreeingwith defendant's vice-president that defendant should augment plaintiff's work force. According[*7]to plaintiff's president, he objected to defendant augmentingplaintiff's work force because there were too many other trades on the site at that time, and heneeded further information about the project to prioritize the work and ascertain the specificnumber of electricians needed at various stages of the project. Although plaintiff's treasurerexecuted the partial waiver and release of lien and accepted the payment, plaintiff's presidenttestified that the treasurer had no choice but to sign the waiver so plaintiff could get paid. Noevidence other than plaintiff's president's testimony supported that assertion.

Plaintiff submitted a requisition for the second installment payment, requesting$250,000.[FN1] By letter dated May 5, 2004, defendant's vice-president advised plaintiff's president that thesecond installment payment would be released after defendant received plaintiff's certifiedpayrolls as well as an executed partial waiver and release of lien. The letter stated, among otherthings: "In terms of the payment amount, as you are aware, [defendant] has taken on a largeportion of [plaintiff's] Fire Alarm work for this project. As it has been discussed with you severaltimes, adjustments to your contract and payment schedule needed to be made in order to accountfor the additional work [defendant] was performing on [plaintiff's] behalf. The costs that[defendant] has incurred will be deducted from each payment accordingly."

By another letter, dated May 6, 2004, defendant's vice-president described the deductionsfrom the second installment payment. The letter contained a detailed description of the costs ofthe work force defendant assigned to work with plaintiff's employees. The letter noted that forthe five-week period covered in the second requisition, defendant's employees had worked a totalof 2,069 hours at the job site with a total labor cost of $163,843.36. Subtracting this sum and theamount of defendant's overhead costs ($14,745.90) from the $250,000 requested by plaintiff andadding a $28,373.33 advance on the third installment payment, defendant offered plaintiff$99,784.07 on its second requisition. Significantly, plaintiff's own invoice for the secondinstallment payment reflects that plaintiff deducted from the amount it requested defendant's"labor costs" and "expense costs." Again, plaintiff's treasurer executed a partial waiver andrelease of lien and plaintiff accepted the payment offered by defendant.[FN2]

Plaintiff's president testified that he did not agree voluntarily to the deductions but, rather,"had no choice" because "[plaintiff] had men working on the job. Um, we needed to get paid,and we needed to pay the union and pay workers, and other expenses that we had. So we had totake whatever they were giving . . . . I basically had no choice. We were notallowed—we [*8]went along." No other evidence,however, supports that assertion and plaintiff's president acknowledged that he never submitted awritten protest to defendant regarding the deductions.

Plaintiff submitted a requisition for the third installment payment, requesting $315,000.Defendant's vice-president responded to this requisition by letter dated June 8, 2004. The letterstated: "As you are aware and as we have advised you in earlier correspondence, [defendant] hasprovided manpower to [plaintiff] in order to expedite the installation of [plaintiff's] contractelectrical work associated with the fire alarm[ ] system . . . When it was decidedthat [defendant] would need to provide additional manpower to assist in [plaintiff's] contractwork, [defendant] immediately informed you that [defendant's] costs associated with thisadditional work performed on [plaintiff's] behalf would be deducted from each of [plaintiff's]contract requisition payments according to all costs incurred up through the date of thepayment."

The letter provided a detailed breakdown of the costs of the work force defendant assignedto work with plaintiff's employees, noting that during the four-week period covered in the thirdrequisition, defendant's employees had worked 4,081 hours at the job site with a total labor costof $353,887.47. This sum, combined with the amount of defendant's overhead costs($31,849.87), exceeded the amount requested ($315,000) by $70,737.34. Thus, defendant'svice-president wrote:

"[P]lease be advised that [plaintiff] is seriously delinquent in the execution of [its]contracting work. In accordance with your submitted proposal and scope of work as well as [the]purchase order . . . the fire alarm system was to be substantially complete by June7, 2004. Please be advised that [plaintiff's] forces are currently only about 30% complete withtheir scope of work. The first floor conduit system has still not been completed and no work hasbeen installed on the second floor by [plaintiff's] personnel. This situation is unacceptable andmore efficient output needs to be achieved by [plaintiff].

"Please be advised that [defendant] is doing everything it can to minimize its exposure on thefire system, however, we do have a schedule to maintain and a contract to abide by.Additionally, we need to ensure that our contractual obligations are being met in the timeframesthat they need to be. Therefore, [defendant] will continue providing the necessary manpower toexecute [plaintiff's] contract work on the fire system as long as [plaintiff] continues providinginsufficient labor and production on the project."

Plaintiff's president testified that he did not agree that the expenses for defendant's costs forperforming work on the fire alarm system should be deducted from the third installmentpayment. Again, however, plaintiff provided no evidence corroborating that it objected to thedeductions.

On June 9 plaintiff demobilized its operations at the job site and abandoned the project.Defendant's vice-president sent plaintiff a letter dated June 11 that stated:

"On Wednesday, June 9, 2004, [plaintiff] de-mobilized from the site and [*9]completely abandoned the . . . project. We must pointout that your abandonment of the project occurred without so much as a phone call,correspondence, or any other type of communication or notification whatsoever.

"Before its abandonment, [plaintiff] was already in breach of its contract. [Defendant], whowas already assisting in the execution of [plaintiff's] subcontract because you were unable orunwilling to do so, will now need to incur substantial additional costs in order to complete thefire system that [plaintiff] was contracted to install. We will hold [plaintiff] responsible for all ofthe associated additional costs and damages."

Plaintiff's president denied that plaintiff did not notify defendant before abandoning theproject. He testified that "[w]e were talking all the time about getting paid, and I let them knowthat if I don't get my money I have no choice. I won't spend any more money at this job, doesn'tmake any sense, especially since they said I owed them $70,000."

On its case, defendant presented one witness, its vice-president, who testified that thepurchase order was a "lump-sum" contract pursuant to which plaintiff would submit requisitionsreflecting the amount of work it had performed and defendant would issue installment paymentsbased on the amount of work completed. Defendant, according to its vice-president, neverguaranteed plaintiff that it would make a profit on the project. Defendant's vice-president statedthat at a meeting shortly before they executed the purchase order, the parties agreed that, onaverage, plaintiff should have between 15 and 18 electricians on the job site but that there shouldbe additional manpower at the site to perform the first phase—the installation of theconduit—which was the most time-consuming and difficult portion of the work.[FN3] Defendant's vice-president also testified that all drawings and specifications for plaintiff's workwere completed and provided to plaintiff before the purchase order was executed.

Withrespect to plaintiff's work on the job site, defendant's vice-president stated that when plaintifffirst began working at the site in the end of February, plaintiff performed several days ofpreparatory work prior to installing conduit on the first floor of the building. Based on plaintiff'scertified payroll reports, defendant's vice-president testified that during its first week at the jobsite, plaintiff had only four to six electricians on the site; during the second week, plaintiffassigned approximately 10 electricians; during the third week approximately 11 electricians; andduring the fourth week, approximately 14 electricians, the most plaintiff ever assigned to the site.

According to defendant's vice-president, he or one of his coworkers called plaintiff'spresident once or twice a week in each of the first three weeks plaintiff was on the project toexpress defendant's concern that plaintiff was not assigning enough manpower to the job site.Plaintiff's president repeatedly responded that he was comfortable with plaintiff's manpowerlevels. However, defendant's vice-president testified that he became nervous during plaintiff's[*10]fourth week on the job and began calling plaintiff'spresident more frequently to inquire as to plaintiff's manpower levels.

With regard to plaintiff's requisition for the first installment payment, defendant'svice-president testified that defendant did not pay plaintiff the $107,350 listed in the purchaseorder because plaintiff had not performed enough work on the site to warrant the full payment.Defendant's vice-president testified that he did not decide unilaterally to reduce the firstpayment. Rather, he called plaintiff's president and wrote him a letter explaining why plaintiffwas only receiving $80,000 on the first installment payment. With regard to the call, defendant'svice-president testified that he expressed his concerns stating: "[T]here wasn't enough workgetting installed to justify the amount of the [full] payment. So we contacted [plaintiff] andexplained that we didn't want to get too far ahead. I explained to him that I went through hiscertified—how much he had spent, how much manpower, and as of—let me stepback—every one time we make a payment it goes through a certain period. . . . Traditional contracts call for the end of the next month . . . . Nowthis was a fast track job and we certainly didn't want to do it to [plaintiff], to have them workingall the way through March 31st and not pay them until the end of April. We didn't think that wasa good way. So we tried to come to some medium ground. If we are going to make a payment onthe end of March, the period cut off, we were about two weeks early. So when I look at thepayment we made to him, I look to the amount of money they spent through March 10th orMarch 13th and I grew concerned because we were scheduled to make a $107,000 payment, andI think at that . . . they had spent thirty something thousand dollars. So I got a littleconcerned knowing that . . . they had all this work left to go, and through arequisition period I would have already paid them, paid them two-and-a-half times what theyspent . . . . I explained to them, I explained to them why we were doing it. I wrote aletter explaining it. We are going to have to reduce your payment based upon this and then the$80,000, I will be very honest, wound up not being an arbitrary amount, I wanted to give themenough money—it was a lot more than he spent—to show them good faith."

The letter to which defendant's vice-president referred is the March 31 letter discussedabove. When asked about the first sentence of that letter—"As per our discussion thismorning, we will be supplying approximately 10 men with a Foreman to perform workassociated with your contract for the Fire Alarm system at the above referencedproject"—defendant's vice-president testified:

"The conversation I am referring to is that the—earlier that morning, um, [plaintiff'spresident] had actually called us and—myself and . . . the President of ourcompany were together in his office when a phone call did come in from [plaintiff's president].In that conversation basically [plaintiff's president] had stated that he was now concerned aboutmanpower and basically was supporting the concerns that we had had for the last five weeks. Inthat phone conversation he asked for our assistance . . .

"He asked for our assistance. Well I really didn't know what he meant. In the initial responsewas [sic] we need you to put more men at the site. That is [the] [*11]only way we are getting it done. He responded that he could notput more men on the site. He was asked in that conversation if we should put men on site. Hedidn't, he didn't respond at that point. [Defendant's president] put [plaintiff's president] on holdand I had a conversation with [defendant's president] about my thoughts on the situation at thispoint because at that point it was my interpretation that he was asking for us to put manpower[on the site]. I actually didn't want to do it. When I explained to [defendant's president] what myreservations were, right now we have a clear delineation in the contract, [defendant] isperforming certain work on this job, [defendant] hired [plaintiff] to do certain work on this job, ifwe put our guys on [plaintiff's] work to do that, to help with that, it was not going to be clean cutand dry, and it wasn't something I thought was not going to be the best way to . . .perform the work . . .

"What I did come up with [during] the conversation, [plaintiff's president's] concern aboutactually paying for the additional men and his requisitioning, he had to put up—he told ushe could not pay for the additional men cash-wise he could not pay for it. So what I suggested to[defendant's president] was I said why don't we ask him to put more men on the site [and] we'llpay him just for the additional labor . . . We have a local union hall with a lot ofelectricians on the site, put more men on the site, keep it under [plaintiff's] employ[ ], we'll pay[plaintiff] once a week for the additional costs, [defendant's president] agreed . . .Then we got [plaintiff's president] back on the line. He told us that he didn't want to do it thatway. We asked him why. He said his other jobs are busy. He didn't want to punish other jobs. Iunderstand that, being a contractor, I understand that you have other contract responsibilities andwith our project you don't want to penalize them. We said unfortunately at this point we'll haveto, to go to the union . . . and hire electricians. We need to put them on site andwork. He informed us at that point that was not a possibility—all he said in response whenwe asked him why, he said the union at that time would not give him additional labor. At thatpoint . . . the reality [wa]s we had to put men on the job at that point because wealso had a contractual obligation to finish our job. We needed to get the job done. Ourelectricians could do the same thing as his electricians could, so at that point we had no otheralternative after he would or could not put more electricians on the job, we had to supplement hisworkers and that is why I am writing this letter."Defendant's vice-president also testified: "[Plaintiff's president] was, he was fully aware andunderstood that in order for us to put electricians on his contract work that we had to pay forevery week, we had to pay benefits every week, we had to pay the payroll every week for theseelectricians, that once a month it . . . needed to come . . . directly outof his monthly requisitions in order for us to pay for them."

After sending the March 31 letter to plaintiff, defendant's vice-president stated that workforce issues continued to plague plaintiff's work. When asked if there "[w]ere any further [*12]discussions after March 31st between [him] and [plaintiff'spresident] concerning the number of electricians that [defendant] was providing to the project for[plaintiff's] account," defendant's vice-president responded: "There were a couplemore—there was definitely a couple more conversations about the amount of manpowerthat [defendant] would need to provide, but maybe one or two, not many because as of thatMarch . . . 31st, after that conversation and after that letter it was basically anunderstanding after that letter was written, after he received the monies, it was basically anunderstanding that we were going to need to provide electricians to perform a certain scope ofwork and his electricians were going to be performing their scope of work." Defendant'svice-president never received any written or verbal communications from plaintiff protesting thearrangement pursuant to which defendant augmented plaintiff's work force, not even afterplaintiff received defendant's letters of May 5 and 6 deducting a substantial sum from plaintiff'srequisition for the second payment.

Defendant's electricians were not, according to defendant's vice-president, simply sent to thejob site without any purpose or assignment. To the contrary, as defendant's vice-presidentexplained: "All of our electricians—this was done on purpose—all of ourelectricians were sent to the second floor. I say it was done on purpose because the secondfloor—as of March 31st or April 1st, our first day—had never been, had never beentouch[ed] in terms [of] the fire alarm. So in order—we spoke to [plaintiff's president], weexplained the easiest delineation here is for your crew to continue on the first floor with yourinstallation and our electricians will begin immediately on the second floor. So we sent ourelectricians to the second floor to begin the fire alarm work."

Defendant's vice-president testified that after defendant began augmenting plaintiff's workforce, the work on the first floor still did not timely progress. He stated that through the firstweek of June, plaintiff had not finished installing the conduit on the first floor, the first phase ofits work on the site. He also stated that plaintiff had "not pulled one foot of wire on the project"and had not installed a single fire alarm device. This testimony was unrebutted.

Defendant's vice-president received a letter from plaintiff's treasurer on or about June 3stating that plaintiff was running a $76,864.53 deficit on the project—$129,649.31 withplaintiff's profit margin factored in—and that plaintiff believed that "the project isoverstaffed" and "suffering from [a] lack of optimal productivity." He also stated that plaintiffwas "not able to absorb any further losses" and requested a meeting to discuss the project.

Defendant's vice-president testified that after receiving the letter, he spoke with plaintiff'streasurer and explained that defendant was also losing money on the project. He also explainedthat the parties had agreed that defendant would augment plaintiff's work force to advance thework. With respect to the letter dated June 8, 2004 in which defendant's vice-president informedplaintiff that it was not entitled to any money on its requisition for the third installment payment(and actually owed defendant $70,737.34), defendant's vice-president noted that he neverreceived any protest, written or otherwise, from plaintiff.

Defendant's vice-president testified that on June 9 he was notified by defendant's [*13]foreman on the job site that plaintiff had demobilized itsoperations and abandoned the project. He further testified that he never received notice fromplaintiff of its decision to abandon the project. Although defendant's vice-president sent theabove-noted letter of June 11 to plaintiff's president, stating that plaintiff was in breach of thepurchase order and was responsible for the cost of completing the work, plaintiff neverresponded to the letter. Defendant's foreman inspected the work plaintiff performed and reportedthat only 60 to 65% of the conduit had been installed on the first floor, no wire had been pulledthrough the conduit, no fire alarm devices had been installed, and only 30% of plaintiff's workunder the purchase order had been completed by plaintiff's electricians. Moreover, the only workdone on the second floor had been performed by defendant's electricians. As a result of plaintiff'sabandonment of the project, defendant was constrained to finish the fire alarm system work.

In its charge to the jury, the court instructed that pursuant to a stipulation, it was agreed thatthe purchase order was the contract between the parties.[FN4] The court noted that plaintiff's claim was that defendant breached the contract by failing to makepayments in accordance with its terms. The court further instructed the jury that to prevail on itsbreach of contract claim, plaintiff was required to prove, among other things, that: (1) plaintiffsubstantially performed its obligations under the purchase order or was excused from furtherperformance by the conduct of defendant; and (2) defendant breached the contract by failing tomake payments required by the purchase order. Conversely, defendant's claim was that plaintiffbreached the contract by both failing to timely progress with the work and abandoning theproject. To prevail on its counterclaim, the court instructed, defendant was required to provethat: (1) it substantially performed its obligations under the purchase order or was excused fromfurther performance by the conduct of plaintiff; and (2) plaintiff breached the contract by failingto advance properly the work as required by the purchase order. Thus, to determine which partybreached the contract, the jury had to determine: (1) when plaintiff was entitled to paymentunder the purchase order; (2) whether the parties agreed that defendant would augment plaintiff'swork force and deduct from plaintiff's payments the costs of the additional labor; and (3)whether plaintiff was prevented from progressing with and completing its work. The jurynecessarily (albeit implicitly) found in favor of plaintiff on each of these points, concluding thatdefendant breached the contract and awarding plaintiff $243,341.99. A judgment wassubsequently entered on the verdict.

On its appeal from the judgment, defendant argues, among other things, that the verdict[*14]was against the weight of the evidence and that the actionmust therefore be retried. For the reasons that follow, I agree.[FN5]

CPLR 4404 (a) provides, in pertinent part, that "the court may set aside a verdict or anyjudgment entered thereon and . . . may order a new trial of a cause of action orseparable issue where the verdict is contrary to the weight of the evidence." As the Court ofAppeals stated in Cohen v Hallmark Cards (45 NY2d 493, 498 [1978]): "In reviewing ajudgment of Supreme Court, the Appellate Division has the power to determine whether aparticular factual question was correctly resolved by the trier of facts. If the original factdetermination was made by a jury, as in this case, and the Appellate Division concludes that thejury has made erroneous factual findings, the court is required to order a new trial, since it doesnot have the power to make new findings of fact in a jury case . . . [T]hedetermination that a factual finding was against the preponderance of the evidence is itself afactual determination based on the reviewing court's conclusion that the original trier of fact hasincorrectly assessed the evidence" (citation omitted). The question of whether a verdict is againstthe weight of the evidence is discretion-laden, and the critical inquiry is whether the verdictrested on a fair interpretation of the evidence (see McDermott v Coffee Beanery, Ltd., 9 AD3d 195, 206 [2004]).The judge's common sense reaction to the evidence (Siegel, NY Prac § 406, at 687 [4thed]), informed by the judge's professional judgment (see id. at 688; Annunziata vColasanti, 126 AD2d 75, 80 [1987], citing Nicastro v Park, 113 AD2d 129, 135[1985]), is the practical test employed to determine whether a verdict rested on a fairinterpretation of the evidence. Notably, a court's discretion to set aside a verdict as against theweight of the evidence " 'is at its broadest when it appears that the unsuccessful litigant'sevidentiary position was particularly strong compared to that of the victor' "(Annunziata, 126 AD2d at 80, quoting Nicastro, 113 AD2d at 136).

The parties stipulated that the purchase order was a binding contract, but they disagreed as towhen plaintiff was entitled to receive payment under the contract. The evidence supportsstrongly defendant's interpretation of the contract. Plaintiff's president testified that he believedthat plaintiff would be paid the installment payments in full on the dates listed in the purchaseorder regardless of the amount of work plaintiff had completed. He also testified that defendantguaranteed plaintiff it would make a profit on the project. The purchase order, though, stated thatthe payment schedule was "subject to change" and that the "[f]ailure to deliver materials orservices in a timely fashion will release contractor from any obligation to purchase implied bythis order" (emphasis added). Thus, the purchase order is inconsistent with the position ofplaintiff's president but is consonant with defendant's vice-president's testimony that the purchaseorder was a "lump-sum" contract pursuant to which plaintiff would submit requisitions reflectingthe amount of work it had performed and defendant would issue installment payments [*15]based on the amount of work completed.

Plaintiff's conduct also suggests that defendant's interpretation of the purchase order iscorrect. After all, plaintiff provided its certified payroll records to defendant as it was processingthe installment payments. If plaintiff were entitled to the installment payments regardless of theamount of work it had performed, resort to those records to calculate the payments would havebeen unnecessary. Moreover, plaintiff's president's testimony that plaintiff was to be paid theinstallment payments regardless of how much work (if any) it had performed and that defendantguaranteed plaintiff it would make a profit on the project not only strains credulity, it is at oddswith the consistent and plausible testimony of defendant's vice-president. Finally, as discussedabove, plaintiff's president's testimony is contradicted by the express terms of the purchase order.

The parties also dispute whether they agreed, after plaintiff began working at the site, thatdefendant would augment plaintiff's work force and deduct the costs associated with doing sofrom plaintiff's installment payments. Plaintiff's president testified that no such agreement wasreached. Defendant's vice-president, however, provided detailed testimony establishing thatplaintiff was not assigning sufficient manpower to the job site and supporting defendant's claimthat the agreement was reached, testimony that was corroborated by extensive documentaryevidence. Defendant's vice-president's letters to plaintiff of March 31, May 5, May 6, and June 8,the executed partial waivers and release of lien forms and plaintiff's own invoice for the secondinstallment payment, individually and collectively, provide compelling support for defendant'sclaim that the parties agreed to defendant's augmentation of plaintiff's work force and deductionof the costs associated therewith from plaintiff's installment payments.

Defendant's vice-president testified that he never received any written or verbalcommunications from plaintiff protesting the arrangement—not even after plaintiffreceived defendant's letters of May 5 and 6 and June 8 deducting substantial sums fromplaintiff's requisitions for the second and third payments. Plaintiff's president acknowledged thatplaintiff never protested in writing either the augmentation of its work force or the resultingsubstantial reductions from the installment payments. In short, plaintiff produced no evidencecorroborating its president's testimony that no manpower augmentation agreement was reached.Given the amount of money defendant was deducting from the installment payments, it borderson the incredible that plaintiff would not have submitted a written protest if there were noagreement that defendant would augment plaintiff's work force.[FN6]

Plaintiff claims that it was prevented from progressing with and completing the work. Thisclaim had two aspects. First, that other trades were working on the job site and hindered [*16]plaintiff's ability to perform its work. Second, that plaintiffrequired additional information to plan and perform its work, information that was neverprovided. The only evidence, however, that plaintiff offered to support this claim was theconclusory, undetailed and uncorroborated testimony of its president. Although plaintiff'spresident testified that other trades hindered plaintiff's ability to perform its work and that heneeded, but never received, additional information regarding the project, he acknowledged thathe never sent a single written request to defendant for further information about the project andnever protested that the plans or specifications were incomplete or inaccurate. In fact, thedocumentary evidence belies plaintiff's claim. Both plaintiff's proposal to defendant for theproject—"We are pleased to submit our proposal for the . . . projectconsistent with the specifications and . . . shop drawings and the [MTA] drawings. . . provided"—and the purchase order—"Project is as per plans andspecifications"—make plain that plaintiff's work was based on plans and specificationsprovided to plaintiff before it executed the purchase order.

Defendant's vice-president testified that other trades would be on the site when plaintiffbegan its work but were simply "standard trades" that are present on most construction projects.Of course, that other trades were on the job site working in proximity to plaintiff's employees isunremarkable—the construction of the facility was a "fast track" project, which plaintiffclearly knew when it submitted its proposal to defendant and executed the purchase order.Defendant's vice-president also testified that all drawings and specifications for plaintiff's workwere complete before the purchase order was executed, and confirmed that no written requestsfor information were sent by plaintiff to defendant.

At bottom, on each material factual question presented at trial with respect to which partybreached the contract—when plaintiff was entitled to payment under the purchase order,whether the parties agreed that defendant would augment plaintiff's work force and deduct fromplaintiff's payments the costs of the additional labor, and whether plaintiff was prevented fromprogressing with and completing its work—defendant's vice-president's testimony wasconsistent, in accordance with common sense, and supported firmly by the documentaryevidence in the record. By contrast, the relevant testimony of plaintiff's president was bereft ofdetail, refuted by the documentary evidence, and, in important respects, at odds with commonsense. In short, the jury's verdict in favor of plaintiff and against defendant is "completely atodds with any fair interpretation of the evidence" (Sepulveda v Aviles, 308 AD2d 1, 9[2003]). Unfortunately, the majority simply defers to the jury's "credibility determinations." Itfails to heed the obligation to scrutinize the evidence adduced at trial and the principle that ourdiscretion to set aside a verdict as against the weight of the evidence is, as noted, " 'at itsbroadest when it appears that the unsuccessful litigant's evidentiary position was particularlystrong compared to that of the victor' " (Annunziata, 126 AD2d at 80, quotingNicastro, 113 AD2d at 136).

Even assuming that the jury's verdict on the issue of breach was not against the weight of theevidence, a new trial would be necessary on the issue of damages. Plaintiff sought $243,341.99,the difference between the amount of money it spent on the project ($375,600.65) and theamount it was paid by defendant ($174,491.57) plus its "allowance for overhead and profit"($42,232.91). Defendant asserted, however, that any award of damages to plaintiff should reflectthat plaintiff's treasurer executed waivers when accepting its first and second payments fromdefendant, precluding plaintiff from recovering any damages sustained during the periodscovered by the waivers. The first waiver covered the period from the date plaintiff beganworking on the project through March 3, 2004, and the second waiver covered the period from[*17]March 4, 2004 through March 31, 2004.[FN7]

Plaintiff asserted that the waivers were unenforceable because defendant procured themthrough economic duress. The only evidence plaintiff adduced in support of this assertion wasthe testimony of its president. He testified that plaintiff's treasurer executed the waivers becauseplaintiff needed the money and the money would only be released to plaintiff if it executed thewaivers. As plaintiff's president put it, "I had no choice. We had men working on the job. . . we needed to get paid, and we needed to pay the union and pay the workers,and other expenses that we had." Later in his testimony, plaintiff's president stated that plaintiff'streasurer was "forced" to sign the waivers because "I needed to get my money" since "I didn'thave any more money to invest in the job." Plaintiff offered no other evidence on this point.

This testimony was patently insufficient to establish that defendant compelled plaintiff toexecute the waivers by means of a wrongful threat that precluded plaintiff from exercising freewill (see Stewart M. Muller Constr. Co. v New York Tel. Co., 40 NY2d 955, 956[1976]). Plaintiff's president's testimony simply does not support the conclusion that defendantthreatened to breach the agreement by refusing to pay plaintiff money owed to it under theagreement unless plaintiff agreed to execute the waivers (see 805 Third Ave. Co. v M.W.Realty Assoc., 58 NY2d 447, 451 [1983]). Rather, the evidence demonstrates that plaintiffsigned the waivers to obtain payments from defendant and that plaintiff did not protest theamounts of those payments at the time the waivers were executed. Plaintiff itself recognized thatit was not entitled to the amount listed in the agreement for the second installment payment butto the amount defendant offered plaintiff; plaintiff's own invoice for the second installmentpayment reflects that plaintiff deducted from the amount it requested defendant's "labor costs"and "expense costs." That plaintiff's president was under financial pressure to meet plaintiff'spayroll and other obligations is simply insufficient to support the jury's implicit finding thatdefendant subjected plaintiff to economic duress (see Gubitz v Security Mut. Life Ins. Co. ofN.Y., 262 AD2d 451 [1999]; Bethlehem Steel Corp. v Solow, 63 AD2d 611, 611[1978], appeal dismissed 45 NY2d 837 [1978], citing Grubel v Union Mut. Life Ins.Co., 54 AD2d 686 [1976]). Because the jury awarded plaintiff the full amount of damagesplaintiff sought and some of those damages were sustained during the periods covered by thewaivers, a new trial on damages would be necessary in any event.

Accordingly, I would reverse the judgment and remand for a new trial. I need not and do notaddress defendant's remaining argument that a new trial must be ordered because the conduct[*18]of plaintiff's president and plaintiff's attorney prejudiced thejury.

Footnotes


Footnote *: The dissent acknowledges thisfact, stating, "The requisition . . . merely demanded the payment specified in thepurchase order."

Footnote 1: The second installment paymentwas listed in the purchase order as $237,500, but plaintiff requested $250,000. It is unclear whyplaintiff requested $12,500 more than was called for in the purchase order for the secondinstallment payment.

Footnote 2: The check defendant sent toplaintiff was for $94,491.57, $5,292.50 less than the amount defendant told plaintiff it wouldreceive on the second installment payment. The partial waiver and release of lien indicated thatplaintiff received $99,784.07. Plaintiff's treasurer noted the discrepancy on the bottom of theexecuted waiver form.

Footnote 3: Defendant's vice-presidentnoted that the conduit called for in the project's specifications was particularly difficult to install.He testified that the conduit was not the "traditional metal tubing" that was used on most projectsbut rather a "galvanized ridged conduit . . . [that is] more difficult to install becausethere is cutting and threading [involved]."

Footnote 4: Plaintiff seems to argue in itsbrief that the judgment, which was the product of a jury's verdict on a claim and counterclaim forbreach of contract, can be affirmed because plaintiff was entitled to recover in quantum meruit.That claim was not before the jury on the verdict sheet; it considered only the competing breachof contract claims. In any event, plaintiff stipulated that the purchase order was an enforceablecontract. Thus, any argument based on quantum meruit is patently without merit (Cox v NAP Constr. Co., Inc., 10 NY3d592, 607 [2008] ["a party may not recover in quantum meruit or unjust enrichment wherethe parties have entered into a contract that governs the subject matter"]; see IDT Corp. v Morgan Stanley DeanWitter & Co., 12 NY3d 132, 142 [2009]).

Footnote 5: Defendant does not assert thatthe verdict was not supported by legally sufficient evidence and that the complaint should bedismissed. Thus, the majority's discussion of the law regarding the legal sufficiency of evidenceand its repeated observation that the verdict is supported by legally sufficient evidence areirrelevant.

Footnote 6: The majority faults defendantfor not calling one of its employees, Evans, as a witness to rebut plaintiff's president's testimonythat he did not protest in writing to defendant because he was in communication with Evans,with whom plaintiff's president had previously worked. That defendant did not call Evans is notremarkable. Defendant's vice-president's detailed testimony was corroborated by the letters hesent to plaintiff. It was plaintiff's president's testimony that was not corroborated by anyevidence. Thus, the appropriate question to ask is why plaintiff did not call Evans.

Footnote 7: The court charged the jury: "Ifyou decide [plaintiff] is entitled to recover from [defendant], you should consider whether inexecuting the partial waivers and releases of liens [plaintiff] waives and releases its claims,claims through the time period of the waivers which is from the beginning of [plaintiff's]performance to March 31, 2004."


NYPTI Decisions © 2026 is a project of New York Prosecutors Training Institute (NYPTI) made possible by leveraging the work we've done providing online research and tools to prosecutors.

NYPTI would like to thank New York State Division of Criminal Justice Services, New York State Senate's Open Legislation Project, New York State Unified Court System, New York State Law Reporting Bureau and Free Law Project for their invaluable assistance making this project possible.

Install the free RECAP extensions to help contribute to this archive. See https://free.law/recap/ for more information.