Metropolitan Steel Indus., Inc. v Tully Constr. Co., Inc.
2008 NY Slip Op 07747 [55 AD3d 363]
October 14, 2008
Appellate Division, First Department
As corrected through Wednesday, December 10, 2008


Metropolitan Steel Industries, Inc., Appellant,
v
TullyConstruction Co., Inc., Respondent, et al., Respondents. Tully Construction Co., Inc., Third-PartyPlaintiff-Respondent, v City of New York, Third-PartyDefendant-Respondent.

—[*1]Schnader Harrison Segal & Lewis LLP, New York (David E. Montgomery of counsel),for appellant.

Peckar & Abramson, P.C., New York (Paul G. Monte of counsel), for Tully ConstructionCo., Inc., respondent.

Michael A. Cardozo, Corporation Counsel, New York (Karen M. Griffin of counsel), forCity of New York, respondent.

Order, Supreme Court, New York County (Herman Cahn, J.), entered March 20, 2008,which, in an action for delay damages by a subcontractor against the project's general contractor,and a third-party action by the general contractor against the site owner for its own delaydamages and for indemnification of plaintiff's claims as well of the claims of "othersubcontractors . . . [which] have demanded or will demand damages by reason ofdelays," denied plaintiff's motion to vacate a prior order staying the action pending completion ofthe project, unanimously reversed, on the facts, without costs, the motion granted and the stayvacated.

The stay was imposed because, in the view of Supreme Court, significant judicial economies,including, in particular, the prospect of "mediation," would be served by awaiting completion ofthe project and receipt of any and all claims by the other subcontractors, and then hearing andconsidering all of the claims together. While the general contractor and owner argue thatcompletion of the project is necessary to determine the impact of all of the delays, neither showhow the alleged errors and oversights in the foundation work, which allegedly caused the [*2]delay in plaintiff's steel erection work, in turn caused, indomino-like fashion, the cumulative delays in the project that have continually pushed itsanticipated completion date back. Absent a showing that any delay damages likely to be claimedby the other subcontractors will be based on the same foundation problems alleged by plaintiff asthe cause of its delay damages, it does not appear sufficiently likely that any significant judicialeconomies will be served by considering all of the subcontractors' claims for delay damagestogether (cf. Schneider v Freres & Co., 159 AD2d 291, 293-294 [1990] [stay imposedpending final determination of another action because other action "raises numerous possibilitiesfor the application of collateral estoppel"]; Belopolsky v Renew Data Corp., 41 AD3d322 [2007]). The owner's request for a severance of the third-party action and stay of allproceedings therein, in the event this Court vacates the stay of the main action, is improperlymade for the first time on appeal, and we decline to consider it. Concur—Friedman, J.P.,Nardelli, Williams and Freedman, JJ.


NYPTI Decisions © 2026 is a project of New York Prosecutors Training Institute (NYPTI) made possible by leveraging the work we've done providing online research and tools to prosecutors.

NYPTI would like to thank New York State Division of Criminal Justice Services, New York State Senate's Open Legislation Project, New York State Unified Court System, New York State Law Reporting Bureau and Free Law Project for their invaluable assistance making this project possible.

Install the free RECAP extensions to help contribute to this archive. See https://free.law/recap/ for more information.