| Lima v NAB Constr. Corp. |
| 2009 NY Slip Op 00653 [59 AD3d 395] |
| February 3, 2009 |
| Appellate Division, Second Department |
| Sidnei Lima, Plaintiff, v NAB Construction Corp.,Respondent, and Tower Painting Co., Inc., Appellant, et al., Defendant. (And a Third-PartyAction.) |
—[*1] McHenry, Horan & Lapping, P.C., Syosset, N.Y. (Jacqueline P. Testani of counsel), forrespondent.
In an action to recover damages for personal injuries, the defendant Tower Painting Co.,Inc., appeals (1) from an order of the Supreme Court, Queens County (Rosengarten, J.), datedJune 22, 2007, which granted the motion of the defendant NAB Construction Corp. for summaryjudgment on its cross claims against the defendant Tower Painting Co., Inc., to recover damagesfor breach of a contract to procure insurance, granted that branch of the separate motion of thedefendant NAB Construction Corp. which was to recover its costs from Tower Painting Co.,Inc., in defending the action, and, in effect, searched the record and awarded summary judgmentto the defendant NAB Construction Corp. on its cross claim against the defendant TowerPainting Co., Inc., for indemnification, and (2), as limited by its brief, from so much of an orderof the same court dated September 18, 2007 as denied that branch of its motion which was forleave to reargue and, upon renewal, adhered to its original determination.
Ordered that the appeal from the order dated June 22, 2007 is dismissed, without costs ordisbursements, as that order was superseded by so much of the order dated September 18, 2007as was made upon renewal; and it is further,
Ordered that the appeal from so much of the order dated September 18, 2007 as denied [*2]that branch of the motion of the defendant Tower Painting Co.,Inc., which was for leave to reargue is dismissed, without costs or disbursements, as no appeallies from an order denying reargument; and it is further,
Ordered that the order dated September 18, 2007 is modified, on the law, by deleting theprovision thereof which, upon renewal, adhered to so much of the original determination in theorder dated June 22, 2007, as (a), upon searching the record, awarded the defendant NABConstruction Corp. summary judgment on its cross claim against the defendant Tower PaintingCo., Inc., for indemnification, and (b) granted that branch of the motion of the defendant NABConstruction Corp. which was to recover its costs from Tower Painting Co., Inc., in defendingthe action, and substituting therefor a provision granting that branch of the motion of thedefendant NAB Construction Corp. only to the extent of awarding it out-of-pocket costs incurredin obtaining and maintaining substitute insurance; as so modified, the order dated September 18,2007 is affirmed insofar as reviewed, without costs or disbursements, and the matter is remittedto the Supreme Court, Queens County, for further proceedings consistent herewith.
The defendant NAB Construction Corp. (hereinafter NAB) demonstrated its prima facieentitlement to judgment as a matter of law on its cross claims against the defendant TowerPainting Co., Inc. (hereinafter Tower), to recover damages for breach of an agreement to procureinsurance. NAB's submissions established that, although Tower obtained a commercial generalliability policy naming NAB as an additional insured, it failed to procure the specific coveragerequired under the insurance provisions of NAB's subcontract with Tower (hereinafter thesubcontract) (see Nrecaj v Fisher Liberty Co., 282 AD2d 213, 214 [2001]; see alsoClapper v County of Albany, 188 AD2d 774, 775-776 [1992]).
In opposition to NAB's prima facie showing, Tower failed to raise a triable issue of fact. Itscontention that NAB waived any claim of breach of the insurance procurement agreement isbelied by the express language in the subcontract providing that NAB's failure to identifyinsurance deficiencies did not relieve Tower from its insurance obligations. Moreover, contraryto Tower's contention, a final determination of its liability for breach of the contract to procureinsurance was not dependent upon "a factual determination as to whose [fault], if anyone's,caused the plaintiff's injuries" (McGill v Polytechnic Univ., 235 AD2d 400, 402 [1997]).Accordingly, the Supreme Court did not err in awarding NAB summary judgment on its crossclaims against Tower to recover damages for breach of a contract to procure insurance.
While the Supreme Court has the power to award summary judgment to a nonmoving party,predicated upon a motion for that relief by another party (see Dunham v Hilco Constr. Co.,89 NY2d 425, 429-430 [1996]), it may not search the record and award summary judgmenton a cause of action if no party has moved for it (see State Farm Fire & Cas. Co. v Browne, 12 AD3d 361, 362[2004]; City Wide Payroll Serv. v Israel Discount Bank of N.Y., 239 AD2d 537, 538[1997]). Here, the record indicates that NAB did not move for summary judgment on its crossclaim against Tower for indemnification. Therefore, the court should not have awarded relief onthat cause of action (see State Farm Fire & Cas. Co. v Browne, 12 AD3d at 362; CityWide Payroll Serv. v Israel Discount Bank of N.Y., 239 AD2d at 538).
Moreover, the Supreme Court erred in granting that branch of the NAB's motion which wasto recover, from Tower, its costs in defending the action. Where, as here, the promisee has itsown insurance coverage, recovery for breach of a contract to procure insurance is limited to the[*3]promisee's out-of-pocket expenses in obtaining andmaintaining such insurance, i.e., the premiums and any additional costs incurred such asdeductibles, co-payments, and increased future premiums (see Inchaustegui v 666 5th Ave.Ltd. Partnership, 96 NY2d 111, 114 [2001]; Netjets, Inc. v Signature Flight Support, Inc., 43 AD3d 1016, 1018[2007]). Accordingly, we remit the matter for a determination of the amount of such costspayable to NAB by Tower.
The parties' remaining contentions are without merit. Skelos, J.P., Angiolillo, Balkin andChambers, JJ., concur.