L & W Supply Corp. v A.D.F. Drywall, Inc.
2008 NY Slip Op 07840 [55 AD3d 1026]
October 16, 2008
Appellate Division, Third Department
As corrected through Wednesday, December 10, 2008


L & W Supply Corporation, Doing Business as Capital Gypsum,Appellant,
v
A.D.F. Drywall, Inc., et al., Respondents, et al.,Defendants.

—[*1]Atlas & Marantz, L.L.P., New York City (Neil G. Marantz of counsel), for appellant.

Cutler, Trainor & Cutler, L.L.P., Malta (Daryl S. Cutler of counsel), for A.D.F. Drywall, Inc.,respondent.

Couch White, L.L.P., Albany (John J. Dowd of counsel), for Federal Insurance Company,respondent.

Rose, J. Appeal from that part of an order of the Supreme Court (Williams, J.), entered June 13,2007 in Saratoga County, which, upon reargument, denied plaintiff's motion for partial summaryjudgment.

Plaintiff furnished building materials that were used by defendant A.D.F. Drywall, Inc. (hereinafterADF), a subcontractor hired by the general contractor, defendant Zandri Construction Corporation, forits work on a public works construction project. Defendant Federal Insurance Company, acting assurety for Zandri, issued a labor and material payment bond on the project. ADF left the job in July2004 without completing its subcontract and failed to pay plaintiff for some of the materials plaintiff hadsupplied. In October 2004, plaintiff filed a mechanic's lien for the cost of those materials. After the lienwas discharged by a bond filed by Federal, again as surety for Zandri, plaintiff [*2]commenced this action to recover the amount owed, and the partiesmoved and cross-moved for summary judgment. To the extent relevant on this appeal, Supreme Courtfound questions of fact and denied plaintiff's motion for summary judgment on the second cause ofaction to recover against the lien discharge bond, the fourth and fifth causes of action to recover on apersonal payment guarantee executed by defendant Jean Lavigne, one of ADF's officers, and the ninthcause of action to recover against the materials payment bond.

As the proponent of the motion for summary judgment on its second cause of action based uponthe mechanic's lien, plaintiff had the burden of presenting evidentiary facts showing the existence of avalid lien and that there were funds due and owing from Zandri to ADF to which the lien could attach(see Lien Law § 4 [1]; LHV Precast v Woodstock Lawn & HomeMaintenance, 296 AD2d 736, 736-737 [2002]; DiVeronica Bros. v Basset, 213 AD2d936, 937 [1995]). In the event that there were insufficient funds available at the time the lien was filed,plaintiff would be limited to any surplus left after deducting the cost to complete ADF's work (seePhilan Dept. of Borden Co. v Foster-Lipkins Corp., 39 AD2d 633, 634 [1972], affd 33NY2d 709 [1973]).

As plaintiff points out, the record contains an affidavit of Jeffrey Lino, the vice-president of Zandri,indicating that ADF was owed $41,335.16 when the lien was filed. However, in its opposition toplaintiff's motion, Federal cited other evidence that Lino had merely stated the amount remaining to beearned by ADF on the subcontract. Federal also alleged that when ADF walked off the job, there was$16,703.16 of its work still incomplete, the project architect had asked for $39,750 in offsets and theproject owner held retainage attributable to ADF's work in the amount of $24,632. Inasmuch as theseoffsets were alleged to have been asserted before plaintiff filed its lien, we agree with Supreme Courtthat there is a question of fact as to the amount, if any, due at the time the lien was filed.

We also agree that Supreme Court properly denied plaintiff's motion for summary judgment as tothe fourth and fifth causes of action, which are based upon a personal guarantee executed by Lavigne in1995. In response to plaintiff's claim that the guarantee applied to all of its sales to ADF, Lavigneaverred that it did not cover materials provided on Zandri's project because two of plaintiff's employeeshad agreed to and did set up a separate billing account for those materials covered by Zandri's paymentbond, rather than the guarantee. Although plaintiff then argued that oral modification of the guaranteewas precluded by the statute of frauds (see General Obligations Law § 15-301 [2]), weare persuaded that Lavigne has raised a triable issue of fact by invoking the partial performanceexception to the statute of frauds (see Rose v Spa Realty Assoc., 42 NY2d 338, 343-344[1977]; Maynard Ct. Owners Corp. v Rentoulis, 235 AD2d 867, 868 [1997]). He haspointed out that plaintiff's invoices on the Zandri project bear a different account number, and he aversthat this was done for the purpose of exempting those purchases from the guarantee. While plaintiff nowargues that there could be other reasons for establishing a separate account number, the record isdevoid of any evidence identifying those reasons. Accordingly, Lavigne's affidavit is at least sufficient toraise a question of fact as to whether the separate account is unequivocally referable to the claimedmodification of the guarantee (see Gross v Vogel, 81 AD2d 576, 577 [1981]; see also Mora v RGB, Inc., 17 AD3d849, 852-853 [2005]; Fairchild Warehouse Assoc. v United Bank of Kuwait, 285 AD2d444, 445 [2001]).

As for the ninth cause of action, we agree with plaintiff that its final invoice to ADF, which listsZandri's project and is dated July 1, 2004, made a prima facie showing that materials were last supplied[*3]to ADF for Zandri's project less than 120 days before it gavewritten notice of its claim against the payment bond, as required to satisfy State Finance Law §137 (see Specialty Prods. & Insulation Co. v St. Paul Fire & Mar. Ins. Co., 99 NY2d 459,466 [2003]). Federal asserted, however, that the last invoice specifying that materials were actuallydelivered to ADF at Zandri's project site is dated April 30, 2004, more than 120 days before noticewas given. Federal further points out that the subsequent invoices covered materials that were pickedup by ADF at plaintiff's facility, rather than delivered by plaintiff directly to Zandri's project, and so onlyADF knows whether those materials were actually used for that project or some other purpose. Giventhat Federal asks for an opportunity to conduct discovery in order to oppose plaintiff's motion(see CPLR 3212 [f]), and also that facts necessary to oppose as to this issue are exclusivelywithin the knowledge of ADF, a party who is adverse to Federal, Supreme Court should have heldplaintiff's summary judgment motion as to the ninth cause of action in abeyance pending such disclosure(see Cassevah v Mack, 51 AD3d1132, 1133 [2008]; Pank v Village of Canajoharie, 275 AD2d 508, 510 [2000];Alston v Golub Corp., 129 AD2d 916, 918 [1987]).

Cardona, P.J., Peters, Kavanagh and Stein, JJ., concur. Ordered that the order is modified, on thelaw, without costs, by reversing so much thereof as denied plaintiff's motion for summary judgment asto the ninth cause of action; motion stayed as to said cause of action pending the expeditious completionof discovery by defendant Federal Insurance Company; and, as so modified, affirmed.


NYPTI Decisions © 2026 is a project of New York Prosecutors Training Institute (NYPTI) made possible by leveraging the work we've done providing online research and tools to prosecutors.

NYPTI would like to thank New York State Division of Criminal Justice Services, New York State Senate's Open Legislation Project, New York State Unified Court System, New York State Law Reporting Bureau and Free Law Project for their invaluable assistance making this project possible.

Install the free RECAP extensions to help contribute to this archive. See https://free.law/recap/ for more information.